Methodology for Evaluating and Optimizing the Selection of Concrete Structure Demolition Methods Based on Cost, Time, and Quality (Safety)
DOI:
https://doi.org/10.61186/JCER.7.2.76Keywords:
Demolish Methods, Concrete silo, Safety, Cost management, Time management, Concrete wire cuttingAbstract
Nowadays, with the aging of old structures and the advancement of construction technologies, demolition projects for outdated structures have seen significant growth. this paper focuses on demolition methods in detail. In a case study conducted in Iran, this paper evaluates the demolition methods for a concrete silo using the Analytical Hierarchy Process (AHP) to select the optimal method based on cost, time, and quality (safety).
Time evaluation is performed using MSP software, while cost assessment for each method is estimated based on resources allocated to the activities within the Work Breakdown Structure (WBS) of each approach. Safety evaluation employs a combined application of the AHP and Data Envelopment Analysis (DEA) methods. Required data for constructing pairwise comparison matrices were gathered through questionnaires completed by domain experts.
The results reveal that the demolition method using concrete wire saws scores the highest among the methods evaluated. Furthermore, based on modeling results in Sap2000 software, it is shown that single-stage toppling of the silo by removing its main columns is not feasible. Subsequently, the site layout design and lifting plan calculations for the selected method were carried out.
All outcomes were compared with real-life execution, and the project's success demonstrated the effectiveness of the chosen method due to comprehensive consideration of all construction management aspects of a demolition project. This paper is written with the aim of simplifying technical concepts in the management of demolition methods.
References
Hufbauer, G. C., and B. W. Severn. "The economic demolition of old buildings." Urban Studies 11.3 (1974): 349-351. https://doi.org/10.1080/00420987420080611 .
Abudayyeh, Osama, et al. "Concrete bridge demolition methods and equipment." Journal of Bridge Engineering 3.3 (1998): 117-125. https://doi.org/10.1061/(ASCE)1084-0702(1998)3:3(117) .
Patel, Ravi. "Demolination method & techniques." Int. J. Res. Sci. Eng. Manag.(nd). (2019).
Assefa, Getachew, and Chelsea Ambler. "To demolish or not to demolish: Life cycle consideration of repurposing buildings." Sustainable cities and society 28 (2017): 146-153. https://doi.org/10.1016/j.scs.2016.09.011 .
Baker, Hannah, Alice Moncaster, and Abir Al-Tabbaa. "Decision-making for the demolition or adaptation of buildings." Proceedings of the Institution of Civil Engineers-Forensic Engineering 170.3 (2017): 144-156. https://doi.org/10.1680/jfoen.16.00026 .
Yuzbasi, Julide. "Experimental verification of full‐scale silo structure demolition: Investigating successive column removal with finite element method and progressive collapse simulation through blast load." Structural Concrete 25.6 (2024): 4408-4427. https://doi.org/10.1002/suco.202400017 .
Huang, Xieping, et al. "Failure analysis of underground concrete silo under near-field soil explosion." Tunnelling and Underground Space Technology 147 (2024): 105696. https://doi.org/10.1016/j.tust.2024.105696 .
Mohammadi, Mohsen, et al. "Advances in Concrete Demolition Technologies: A Review of Conventional and Emerging Methods for Sustainable Waste Management." Eng 5.4 (2024): 3174-3191. https://doi.org/10.3390/eng5040167 .
Keshavarz Mirza Mohammadi, Payam, Seyed Hamed Khalilpour, and Pooya Sareh. "Simulating the response of buried structures to external blast loads: methods, challenges, and advances." Engineering Reports 5.6 (2023): e12607. https://doi.org/10.1002/eng2.12607 .
Wang, Tianqi, et al. "Time–cost–quality trade-off analysis for planning construction projects." Engineering, Construction and Architectural Management 28.1 (2021): 82-100. https://doi.org/10.1108/ECAM-12-2017-0271 .
Thomas L. Saaty. Fundamentals of Decision Making and Priority Theory with the Analytic Hierarchy Process. New York: RWS Publications, 2000.
Sánchez-Garrido, Antonio J., Ignacio J. Navarro, and Víctor Yepes. "Multi-criteria decision-making applied to the sustainability of building structures based on Modern Methods of Construction." Journal of Cleaner Production 330 (2022): 129724. https://doi.org/10.1016/j.jclepro.2021.129724 .
Chen, Zhen-Song, et al. "Expertise-based bid evaluation for construction-contractor selection with generalized comparative linguistic ELECTRE III." Automation in Construction 125 (2021): 103578. https://doi.org/10.1016/j.autcon.2021.103578 .
Gharouni Jafari, Kobra, Nozhat Sadat Ghazi Sharyatpanahi, and Esmatullah Noorzai. "BIM-based integrated solution for analysis and management of mismatches during construction." Journal of Engineering, Design and Technology 19.1 (2021): 81-102. DOI: https://doi.org/10.1108/JEDT-02-2020-0044 .
Len Holm and E. John Schaufelberger. Construction Cost Estimating. London & New York: Taylor & Francis, 2021.
Technical Regulations for Explosives and Rock Blasting in Mines No. 410. Islamic Republic of Iran, 2008.
Jangl, Stefan, Vladimir Kavicky, and Michal Pilat. "Design of bridge blasting demolition." MATEC Web of Conferences. Vol. 352. EDP Sciences, 2021. DOI: https://doi.org/10.1051/matecconf/202135200002 .
Lamond, Joseph F., et al. "Removal and reuse of hardened concrete." American Concrete Institute: Farmington Hills, MI, USA 26 (2001)..
Mohajeri, M., and A. Ardeshir. "Analysis of construction safety risks using AHP-DEA integrated method." Amirkabir Journal of Civil Engineering 48.3 (2016): https://doi.org/10.22060/ceej.2016.608
Badri, Adel, Sylvie Nadeau, and André Gbodossou. "Proposal of a risk-factor-based analytical approach for integrating occupational health and safety into project risk evaluation." Accident Analysis & Prevention 48 (2012): 223-234. https://doi.org/10.1016/j.aap.2011.05.009 .
Wang, Ying-Ming, Jun Liu, and Taha MS Elhag. "An integrated AHP–DEA methodology for bridge risk assessment." Computers & industrial engineering 54.3 (2008): 513-525. https://doi.org/10.1016/j.cie.2007.09.002 .
Walker, Kenneth K., et al. "Methods and procedural considerations in demolishing tall concrete chimneys." Journal of construction engineering and management 122.3 (1996): 223-230. https://doi.org/10.1061/(ASCE)0733-9364(1996)122:3(223) .
Shalenny, Vasiliy. "Safe technologies for cutting reinforced concrete structures by means of diamond tools." E3S Web of Conferences. Vol. 97. EDP Sciences, 2019. https://doi.org/10.1051/e3sconf/20199703009 .
Menon, Arathy H., and Geetha K. Jayaraj. "Comparative study of demolition methods." INTERNATIONAL JOURNAL 2.2 (2017).
Vishwajeet Rajkumar Shedge. “Technological Innovations in Demolition Equipment and Methods.” International Journal of Research in Engineering, Science and Management 7.6 (2024): 35–39.
Baragetti, Sergio, Marco Giustinoni, and Fabrizio Ranghetti. "Wire ropes with diamond beads for multi-wire machines optimization by means of DoE: Numerical models and choice of design parameters." Engineering Failure Analysis 143 (2023): 106826. https://doi.org/10.1016/j.engfailanal.2022.106826
Denkena, Berend, Benjamin Bergmann, and Björn-Holger Rahner. "A novel tool monitoring approach for diamond wire sawing." Production Engineering (2021): 1-8. https://doi.org/10.1007/s11740-021-01087-7
Guidelines for Lifting Plan Development. Workplace Safety and Health (WSH) Council, September 2023.
NK-1200 Fully Hydraulic Truck Crane Lifting Capacity 120T. KATO.
D. E. Elbeltagi. Site Layout Planning. Mansoura University.